Consultancy
Our methods:
what we use to find capacity β and to prove it
We do not bring one method to every plant. We bring a portfolio. We first analyse, so you see the potential in man-hours and euros. Then we change the floor together with your team, make the results visible on the wall, and verify them with your own data.
- Analyse
- Decide
- Intervene
- Verify
Analysis
Analysis β what we find
Before anyone builds, rents or buys, we measure.
- Structured diagnostic β from 2 days to 3 weeks. In one shipyard diagnostic we interviewed 99 people.
- Assessment grid on 8 axes β one page that shows where the plant stands.
- DILO (a day in the life of) β we follow a foreman or supervisor minute by minute for a full shift.
- Cycle-time studies and work sampling β timing per operation, losses by category.
- Takt versus cycle time, OEE β where the line loses its pace.
- Value stream mapping (VSM) β the current and the future flow on one sheet.
- 4M / Ishikawa and Pareto β causes, ranked.
- Warehouse capacity model β locations, density, picking methods, options.
- Inventory analysis β MOQ, lot size, ABC/XYZ, obsolete stock.
- Make-or-buy and logistics network models β the cost of each option.
- ROI and payback β investment against yearly gain.
- Opportunity log β each measure with its yearly benefit in man-hours and euros, and a status: identified, agreed, installed.
- Active supervision17%
- Administration19%
- Training1%
- Other63%
Intervention β what we change on the floor
Together with your people, on the floor, not in a meeting room.
- Shop-floor management on three levels β shift (daily, 10 minutes), section (weekly), plant (monthly), with standard agendas.
- OBEYA and SQDC boards β safety, quality, delivery, cost on one wall.
- Validated standard hours β planned against actual, per block or section.
- Resource balancing with production scheduling β in one programme, 283 people instead of 345 for the same plan.
- 5S and min-max stock β a place for everything, a limit for every stock.
- Layout and storage redesign β in one plant, loaded racks were moved and a mezzanine built in four days, without stopping production.
- Kanban and supermarket β material reaches each position before the line stops.
- Kaizen wall β ideas, owners, status, visible to everyone.
- Procedures and work instructions β the new way, written down.
- Software when paper is not enough β the indicator goes live.
Before345 people
After283 people
Visual management β what you see on the wall
If it is not on the board, it is not managed.
- A board system on three levels, with colour codes: shift boards, section boards, plant board. At one shipyard: 13 shift boards.
- One KPI per sheet: its written definition, the target, the owner by name, a red or green mark every week.
- KPI definitions agreed in advance: at one automotive plant, 18 logistics KPIs were defined before the boards went up.
- Shift boarddaily
- escalates to
- Section boardweekly
- escalates to
- Plant boardmonthly
Audit and verification β how we prove it
A result counts only when it is measured the same way before and after, from your data.
- Monthly 5S audits on 25 criteria. In one cutting area the score rose from 32% to 64%.
- Management HSE audits and layered process audits (LPA).
- KPI calculation rules agreed with you before the start.
- Before and after on defined weeks, from your own data source.
- Monthly progress reports signed by the client.
- Leadership behaviour assessments, scored per leader, before and after.
- AI-in-supply-chain checklist β 83 checks (AI Act, GDPR, NIS2, Machinery Regulation) before you buy an AI tool.
Before32%
After64%
Coaching β so it stays when we leave
The method stays in the plant only if the leaders run it.
- 1:1 leadership coaching, led by Raul PantiΘ: a behaviour assessment for each leader, a personal development plan, coaching on shop-floor management, process confirmation and policy deployment. Used at an automotive wire-harness plant (4 leaders) and at a shipyard (4 leaders).
- Planning coaching β the planning team learns to run the new routine.
- Lean training inside the project β Lean thinking, problem solving, 5S. At one shipyard: 127 participations.
Which methods fit your plant depends on the decision you face. In 20 minutes we tell you where we would start.