How can a large-scale infrastructure project overcome operational hurdles and increase its productivity by 27%?

Share IT Smart Team
13 min read

In an international shipbuilding and road construction context, an ambitious project to build an extended-length bridge faced critical delays, planning deficiencies and a lack of effective organisational alignment. Share It Smart has intervened with an integrated strategy of optimization, digitization and streamlining of production flows, managing to generate significant improvements.

How can a large-scale infrastructure project overcome operational hurdles and increase its productivity by 27%?

The Client and General Context

Our client, a global leader in shipbuilding and road infrastructure, aimed to build a long bridge using large metal modules. The project required strict adherence to quality and efficiency standards, which was essential for its success.

Strategic Collaboration

This collaboration was crucial for delivering a safe, sustainable project meeting international standards. The combined expertise of shipbuilding excellence and world-class design ensured the highest quality outcomes.

Shipyard Partner

Responsible for manufacturing metal modules due to its expertise and high-quality infrastructure

Japanese Designer

Recognized for its advanced design and strict quality standards, ensuring module compliance with international technical requirements

Project Challenges

Problem
Significant Production Delays
Potential Impact
First module took 3x longer than planned; working time remained nearly double the estimates
Problem
Inadequate Quality Standards
Potential Impact
Manufactured modules failed to comply with strict designer standards and international requirements
Problem
Lack of Organizational Alignment
Potential Impact
Significant divergences between divisions regarding targets and unclear role definitions causing decision blockages
Problem
Poor Coordination Systems
Potential Impact
Distinct and non-aligned schedules between divisions hampering collaborative efficiency
Problem
Inefficient Time Utilization
Potential Impact
Only 50-60% of total time was productive, resulting in significant resource waste
Problem
Absence of Visual Management
Potential Impact
No system to track progress and escalate problems, leading to reactive rather than proactive management

Detailed Situation Analysis

The Share IT Smart and Lean Performance consulting teams conducted a comprehensive assessment, identifying critical pain points across all operational dimensions.

Project Management Issues

Fundamental structural problems affecting coordination and execution

  • •Lack of a unified target model and performance indicators (KPIs)
  • •Overlapping managerial roles generating uncertainties and decision-making blockages

Planning Deficiencies

Critical gaps in scheduling and data management

  • •Absence of a centralized scheduling system
  • •Inconsistent data across divisions affecting execution consistency

Production Flow Inefficiencies

Operational bottlenecks reducing productivity

  • •High unproductive time due to lack of visual management system
  • •No strategy to reduce downtime (e.g., equipment changeover optimization)

Quality and Maintenance Gaps

Process misalignment affecting output quality

  • •Maintenance process not adapted to production pace
  • •Persistent non-conformities in manufactured modules

Comprehensive Solutions Implemented

An integrated transformation approach addressing all critical areas through strategic interventions and innovative methodologies.

Managerial Alignment

Creating organizational unity through clear structures and objectives

  • •Establishing a single unified target for all involved divisions
  • •Creating clear structure of joint meetings based on production data
  • •Escalating critical issues to higher decision-making authorities

Scheduling Optimization

Implementing advanced planning tools for resource efficiency

  • •Development of scenario simulation tool for optimal resource allocation
  • •Implementation of centralized scheduling system eliminating data inconsistencies

Production Flow Streamlining

Enhancing operational efficiency through systematic improvements

  • •Introducing visual management system to track progress and escalate issues
  • •Applying SMED process to reduce downtime and improve changeover efficiency
  • •Structuring daily meetings to resolve critical problems rapidly

Quality Assurance Enhancement

Ensuring compliance with international standards

  • •Adapting processes to meet strict quality standards
  • •Implementing rigorous quality control methods and checkpoints

Outstanding Results Achieved

27%

Productivity Increase

18%

Staff Reduction

100%

On-Time Delivery

Project completed within budget and established deadlines

Considerable financial savings generating long-term value

Sustainable performance model established for future projects

Strategic Success Factors

Integrated Approach Excellence

Demonstrated that combining operational optimization, managerial alignment, and digitalization delivers transformative results

Sustainable Performance Model

Created a replicable framework enabling consistent high performance across future projects

Quality and Efficiency Balance

Proved that strict quality standards and operational efficiency can coexist and reinforce each other

Partnership Synergy

The collaboration between Share IT Smart, Lean Performance, and client teams created exceptional value

Building the Future of Infrastructure

The bridge project demonstrates that even the most complex infrastructure challenges can be overcome through integrated operational excellence, strategic alignment, and systematic process improvement

Share IT Smart and Lean Performance delivered not just a completed project, but a sustainable operational model that continues generating value

This transformation approach is replicable across large-scale infrastructure projects, creating lasting competitive advantages for organizations committed to operational excellence

Related Case Studies

More Success Stories

Explore how we've transformed operations across different industries

How do you double the storage capacity in 5 days, without downtime or risks?
View Case Study
Consultancy

How do you double the storage capacity in 5 days, without downtime or risks?

After the relocation of the production lines, BCS Timisoara faced a major logistical bottleneck, which jeopardized the continuity of production and compliance with IATF standards. Share it Smart intervened with an integrated solution for operational optimization and rapid reorganization of the warehouse - implemented without interruptions in just 5 days.

Read Full Case Study
The Importance of the RFQ Process in Carrier Selection - Real Data Obtained with QCLOT
View Case Study
QCLOT

The Importance of the RFQ Process in Carrier Selection - Real Data Obtained with QCLOT

We demonstrate the importance of a systematic and controlled RFQ (Request for Quotation) process in the logistics activity of a production company, using real data obtained through the QCLOT platform. We emphasize the financial benefits, operational efficiency and risks associated with the lack of competition or absence of this process.

Read Full Case Study
How can a shipyard reduce operational equipment costs by more than 500,000 euros in the first year?
View Case Study
ERM

How can a shipyard reduce operational equipment costs by more than 500,000 euros in the first year?

A prestigious shipyard, part of an international group, was facing inefficient resource management, poor planning and the lack of a digital monitoring system. Through an advanced digital solution, Share It Smart has implemented an intelligent planning and optimization system, generating significant cost savings and operational improvements.

Read Full Case Study