How do you double the storage capacity in 5 days, without downtime or risks?

Share IT Smart Team
10 min read

After the relocation of the production lines, BCS Timisoara faced a major logistical bottleneck, which jeopardized the continuity of production and compliance with IATF standards. Share it Smart intervened with an integrated solution for operational optimization and rapid reorganization of the warehouse - implemented without interruptions in just 5 days.

How do you double the storage capacity in 5 days, without downtime or risks?

Context and Initial Challenges

BCS Timișoara provides electronic solutions for the automotive industry and other fields with demanding standards. The relocation of production lines led to a sudden increase of more than 60% in the volume of parts, which led to the capacity of the existing warehouse being exceeded. In order to maintain the activity, temporary storage spaces (pallets in general areas) were used.

Critical Issues Requiring Immediate Action

  • ✕Frequent shutdowns of production lines
  • ✕Difficult access and operational risks
  • ✕Low inventory accuracy
  • ✕Non-compliance with IATF 16949 and occupational safety standards

BCS Timișoara - Electronics & Automotive

Active in the electronics and automotive industry, went through a process of relocating production lines that generated an increase of over 60% in the volume of managed components.

Analysis of the Situation

The Share IT Smart team carried out a detailed analysis of the existing space and processes:

  • •Direct observation of workflows and working methods
  • •Analysis of the degree of use of space and equipment
  • •Simulation of moving scenarios using the cardboard engineering method

Main Causes Identified

Problem
Infrastructure not adapted to new volumes
Potential Impact
Unable to accommodate 60% increase in component volume
Problem
Inefficient manual handling
Potential Impact
Increased operational time and safety risks
Problem
Lack of a flexible inventory organization model
Potential Impact
Temporary storage in general areas causing production disruptions
Problem
Non-compliance with IATF 16949 standards
Potential Impact
Audit risks and potential certification issues

Implemented Solutions

A comprehensive approach combining physical infrastructure improvements with innovative logistics concepts.

Operational Optimization

Strategic infrastructure improvements for enhanced efficiency.

  • •Construction of a two-level warehouse with a mezzanine accessible without heavy lifting equipment
  • •Strategic redefinition of inventory organization to increase safety, operator efficiency and reduce the need for specialization (e.g. forklift drivers)

Innovation and Mobility

Revolutionary mobile warehouse concept.

  • •Introduction of a completely new concept of 'mobile warehouse': shelves were lifted and mounted on wheels without being emptied of stored materials, allowing them to be moved as a whole, together with stocks, without disorganization

Project Management and Collaboration

Coordinated implementation with key partners.

  • •Full coordination of the implementation by Share IT Smart
  • •Active involvement of the customer in defining safety requirements
  • •Selection of specialized suppliers: Concita for moving loaded shelves, Tudox for shelf extension and mezzanine construction

Managing Critical Constraints

Delivering results under extreme time pressure.

  • •Implementation in just 5 days, including 2 weekend days
  • •Zero production stoppages during the entire process
  • •Full compliance with strict safety and fire risk prevention requirements

Transformation Delivered in 5 Days

Results and Impact

80%

Storage Capacity Increase

0

Production Interruptions

4,500

Final Storage Locations

Inventory accuracy significantly improved

Faster access to components and efficient handling

Full compliance with IATF 16949 standards and occupational safety requirements

Sustainable solution enabling future growth

Scalability and Sustainability of the Solution

A future-proof approach designed for long-term operational excellence.

Extensibility

Modular design enabling rapid adaptation.

  • •The modular mezzanine can be replicated in other areas
  • •The organization model with mobile shelves allows quick adaptations to variable volumes

Sustainability

Long-term efficiency and cost optimization.

  • •The organization favors cyclical inventory management
  • •Eliminating heavy equipment reduces costs and risks
  • •Operators are focused on value-added tasks, increasing overall efficiency

Replicable Model

Creating an internal benchmark for excellence.

  • •The project becomes an internal benchmark for rapid logistics reorganizations in critical contexts

Key Takeaways

Speed Without Compromise

Demonstrated that even the most pressing logistical challenges can be solved rapidly without sacrificing quality or safety

Innovation in Action

The mobile warehouse concept proved that unconventional thinking can deliver breakthrough results

Zero Downtime Achievement

Successfully doubled capacity while maintaining 100% production continuity

Strategic Model

Created a replicable framework for rapid logistics transformation in critical environments

Read more about this project on LinkedIn

View LinkedIn post

Building the Future of Logistics

Share IT Smart offers not only technical implementations, but also a replicable strategic model, with visible and sustainable impact

If your organization needs agile solutions in critical environments, we are ready to build, together, a new standard of logistics efficiency

This approach combines operational expertise with rigorous planning to deliver rapid, sustainable transformations

Related Case Studies

More Success Stories

Explore how we've transformed operations across different industries

How can a large-scale infrastructure project overcome operational hurdles and increase its productivity by 27%?
View Case Study
Consultancy

How can a large-scale infrastructure project overcome operational hurdles and increase its productivity by 27%?

In an international shipbuilding and road construction context, an ambitious project to build an extended-length bridge faced critical delays, planning deficiencies and a lack of effective organisational alignment. Share It Smart has intervened with an integrated strategy of optimization, digitization and streamlining of production flows, managing to generate significant improvements.

Read Full Case Study
The Importance of the RFQ Process in Carrier Selection - Real Data Obtained with QCLOT
View Case Study
QCLOT

The Importance of the RFQ Process in Carrier Selection - Real Data Obtained with QCLOT

We demonstrate the importance of a systematic and controlled RFQ (Request for Quotation) process in the logistics activity of a production company, using real data obtained through the QCLOT platform. We emphasize the financial benefits, operational efficiency and risks associated with the lack of competition or absence of this process.

Read Full Case Study
How can a shipyard reduce operational equipment costs by more than 500,000 euros in the first year?
View Case Study
ERM

How can a shipyard reduce operational equipment costs by more than 500,000 euros in the first year?

A prestigious shipyard, part of an international group, was facing inefficient resource management, poor planning and the lack of a digital monitoring system. Through an advanced digital solution, Share It Smart has implemented an intelligent planning and optimization system, generating significant cost savings and operational improvements.

Read Full Case Study